S-34.1, r. 1 - Regulation respecting petroleum exploration, production and storage in a body of water

Full text
174. The authorization holder must install production tubing if the fluid withdrawn or injected is corrosive for the casings.
The authorization holder must design and install the casing and production tubing so as to comply with the Industry Recommended Practice, IRP: #25, Primary Cementing, published by the Drilling and Completions Committee.
O.C. 1251-2018, s. 174.
In force: 2018-09-20
174. The authorization holder must install production tubing if the fluid withdrawn or injected is corrosive for the casings.
The authorization holder must design and install the casing and production tubing so as to comply with the Industry Recommended Practice, IRP: #25, Primary Cementing, published by the Drilling and Completions Committee.
O.C. 1251-2018, s. 174.